Project

General

Profile

Copy Actions

Bug #17

closed
SP MV

Switch ON more than 3 machines to analyse the exact issue and split the units for 2 more customers(2 units for Sabith customer and 2 units for greenair team)

Bug #17: Switch ON more than 3 machines to analyse the exact issue and split the units for 2 more customers(2 units for Sabith customer and 2 units for greenair team)

Added by Soujanya Pydakula 3 months ago. Updated about 2 months ago.

Status:
Closed
Priority:
High
Start date:
09 Jul 2026
Due date:
10 Jul 2026
% Done:

0%

Estimated time:
2:00 h

Add

Subtasks


Add

Related issues

MV Updated by Maniteja Vadnala about 2 months ago Actions #1

  • Status changed from In Progress to Closed
Copy Actions